The Uganda Electricity Distribution Company Limited (UEDCL) has announced a series of infrastructure upgrades aimed at addressing persistent electricity outages affecting parts of Greater Kampala and Wakiso District.
The interventions include upgrading the electricity network at Kawanda Substation, expanding distribution infrastructure and increasing power capacity to meet growing demand from residential, commercial and industrial consumers.
UEDCL said the Uganda Electricity Transmission Company Limited (UETCL) had granted additional power capacity to address recent supply constraints affecting Kakiri, Kawempe, Matugga, Bombo, Namugongo, Magigye, Gayaza, Manyangwa, Nakwero, Namulonge and surrounding communities.
As part of the intervention, UEDCL is upgrading the interconnecting electricity line at Kawanda Substation to facilitate the reliable distribution of the additional power.
The company explained that the original underground copper cable design had been replaced with an overhead line to improve security, simplify maintenance and minimise disruptions caused by vandalism and electricity infrastructure theft.

UEDCL Area Engineer, Eng. Peter Mwondha, said 17 pole structures had already been erected, with engineers proceeding with the installation of overhead electricity lines.
“Our teams have already erected 17 pole structures and are now stringing the lines, with completion expected this weekend. Once finalised, power reliability will significantly improve for over 4,000 customers in Kakiri, Kawempe and Namulonge,” Mwondha said.
He thanked residents for their patience and cooperation during the ongoing works, urging the public to keep away from construction sites and report electricity theft or infrastructure vandalism to UEDCL, local council authorities or the nearest police station.
The announcement comes amid growing public concern over unreliable electricity supply, particularly in the Greater Kampala Metropolitan Area and neighbouring communities.
UEDCL Acting Managing Director, Eng. Joselynne R. Rwabwogo, said the company was implementing immediate, short-term, medium-term and long-term interventions to address electricity supply challenges in Greater Kampala and Wakiso District.
Rwabwogo acknowledged that some communities continued to experience significant supply constraints, partly because rapid industrial and residential expansion had outpaced the capacity of existing electricity infrastructure.
In the Greater Bombo area, she identified capacity limitations at Kawanda Substation and Magigye as major factors affecting electricity consumers.
“UETCL and UEDCL are at an advanced stage of implementing an increase in capacity at Kawanda Substation from 40 MVA to 80 MVA before the end of this year,” Rwabwogo said.
She revealed that land had already been acquired for the proposed Matugga Substation, while the necessary equipment was under manufacture.
The investment is expected to substantially ease electricity supply constraints in the area by the second quarter of 2027.
Rwabwogo also highlighted growing electricity demand along Hoima Road, particularly in Wakiso and Nansana, where rapid industrialisation and residential development have placed additional pressure on the existing distribution network.
She said a contractor was mobilising to construct a second electricity line from Kakiri Substation, where an additional transformer had already been installed.
“These are among several interventions underway, with more projects at different stages of implementation and mobilisation,” she said.
The planned upgrades form part of UEDCL’s broader efforts to strengthen electricity distribution infrastructure, improve supply reliability and accommodate increasing demand from households, businesses and industries.
The success of the projects is expected to ease capacity constraints, reduce power interruptions and support economic activity across the affected communities.